Tied
for 1st place with Wildcat Construction (another
member of the Sherwood Companies), the 45 million
dollar project had two areas that were a challenge
and led to us getting the award.
The first was inherent to
the project. The plans required the Contractor,
in
successive seasons, to work at the main crossroads
to downtown Newton, Broadway and 1st Streets,
remove the existing bridge over I-135, elevate
I-135 over the side streets and rebuild them
under
I-135. In other words, before we started the
side street traffic ran over I-135 but when
it was
finished, the I-135 traffic ran over the side
street.
The second item concerns
a problem that was discovered at the end of
the
2001 season. The shoulders on the ramps to the
Broadway bridge had been placed before it
was
realized they were inadequately reinforced to
meet standards. During the winter of 2002,
Sherwood
worked closely with KDOT to remove the shoulders
already poured and replace them with the correctly
designed sections. This work was done over the
winter because it had to be done before the
2002
work could start. If it wasn't started on time,
the 2002 work could have run into the 2003
season.
|
 
One
of the reasons we won this award was a location
on the project that called for a new box culvert
to be built, but had to be built in two phases
because of the proximity to the old road that
would be eradicated after traffic was placed
on
the new road. When we excavated for the Phase
II box work it was noticed that the box that
had
already been built was showing signs of distress.
Upon checking it was discovered that it had
been
designed for 10 feet of backfill height instead
of the 30 feet that it was already carrying.
Several
options were pursued to correct this problem
but none were very workable or cost effective.
The
box size at this location was 8 feet wide and
7 feet high and it was finally suggested to
KDOT
to consider a precast box that could be placed
inside the existing box in the deficient section.
KDOT redid the analysis of the drainage area
and
was able to use a precast box that was 6 feet
wide and 5 feet high.
The next challenge was finding
a way to move the precast boxes inside the exiting
box since there were 29 sections that were 6
feet long and each one weighed approximately
12,000 pounds. A framework was designed and built
in the Sherwood weld shop using heavy-duty casters
that had previously been in service at Boeing.
The framework was placed inside the box section
and hydraulic jacks were placed on top of the
framework. By jacking against the top of the
box
the weight of the box was transferred to the
framework.
The next step was rolling
the box section into place, which was done
with
the help of a skid loader. After the box section
was winched into place the framework was disassembled
and taken back for the next section. Personnel
from Klaver Construction (a member of the
Sherwood
Companies) had the task of placing the box sections
and this work was accomplished in only two
days.
The next task was grouting the space between
the two boxes and Wildcat Concrete Services
(another
member of the Sherwood Companies) was called
in for this work. Unfortunately, the weather
had
turned quite cold when they arrived and although
both ends of the box could be closed for the
grout
to stay warm while it cured, the grout machine
had to stay outside. Employees of Wildcat
Concrete
Services ingeniously solved this by building
a temporary enclosure around the entire grout
truck
and placing heaters inside the enclosure. This
is a good example of using the strengths of
several
of the Sherwood Companies to work with KDOT in
a partnering situation.
|